 Pembangunan Gazebo di Lima Pulau Sudah 85 Persen

Pramuka Island Plaza Pier Construction Has Touched 85 Percent

The construction of Pramuka Island Plaza Pier, Panggang Island Urban Village, North Seribu Islands has reached 85 percent. It is targeted to be completed by the end of this month.

We spend Rp 4.5 billion to build the pier

"The project has reached 85 percent," said Suherman, Section Head of Facility and Infrastructure for Seribu Islands Transportation Sub-dept., Thursday (11/2).

He stated, thus far, it has entered stage of rubber installation on the side of the pier to hold the boat leaning. "Next is the installation of the archway and continued with arrangement of conblock," he expressed.

Liquor and Expired Food Confiscated from Pramuka Island

He added the plaza pier design is altered extending from the UPAPK to the end of the RPTRA, shaped like V.

"We spend Rp 4.5 billion to build the pier," he closed.

Linked News
Popular News indeks
  1. Jakarta to Hold Citywide Lights-Out Initiative

    access_time24-04-2026 remove_red_eye774 personAldi Geri Lumban Tobing
  2. Suckerfish Handling in South Jakarta is Run in Accordance with MUI Recommendations

    access_time21-04-2026 remove_red_eye658 personTiyo Surya Sakti
  3. Jakarta Residents Welcome Rp1 Public Transport Fare

    access_time24-04-2026 remove_red_eye559 personNurito
  4. Limiting Gadget Use in Schools Expected to Boost Interaction and Reading Habits

    access_time24-04-2026 remove_red_eye546 personFakhrizal Fakhri
  5. Rano Leads Parking Arrangement on Jalan R.A. Kartini, Lebak Bulus

    access_time24-04-2026 remove_red_eye545 personBudhi Firmansyah Surapati